Problem
A leading chemical plant experienced production disruption due to turbine failure attributed to lubricant degradation. After acquiring a new turbine, the third-party flushing company required 10 days of downtime to facilitate a chemical flush.
Solution
Fluitec utilized 10% of DECON™ to clean the entire system before placing Infinity TO into the new turbine.
Results
DECON achieved system cleaning in 6 days without requiring equipment shutdown, averting additional delays. Infinity TO, with a 10-year life guarantee, eliminates the necessity for future flushing or decontamination.